Energy Fuels plans 1 million-pound uranium run at Utah's White Mesa Mill

Processing starts in December near Blanding, while crews rehab a hoist at Energy Queen and drill permitting wells at Bullfrog.

Darren Eastman
Darren Eastman

Nov 23, 2026

Energy Fuels plans 1 million-pound uranium run at Utah's White Mesa Mill

Construction news brought to you by Utah Safety Consultant.

AI-generated illustration of a uranium ore processing mill with green processing tanks, yellow catwalks and ore stockpiles on a red-rock mesa in southeastern Utah

Illustration generated with AI, not a photo of the White Mesa Mill.

Energy Fuels Inc. plans to restart uranium processing at its White Mesa Mill near Blanding in December, a run the company expects to turn out roughly 1 million pounds of finished uranium concentrate before the mill switches back to rare earth production, the company announced Monday.

The campaign is expected to run through the first quarter of 2027. The mill will process ore and mineralized material from the company's Pinyon Plain mine in Arizona and its La Sal Complex in Utah, along with other uranium-bearing "alternate feed" materials. The finished concentrate, known as U3O8, will be shipped to a North American conversion facility.

Energy Fuels calls White Mesa the largest conventional uranium processing facility in the United States and the only fully licensed and operating conventional uranium mill in the country. A U.S. Department of Labor spokesperson told Skillings Mining Review it is also the only uranium mill in the country regulated by the Mine Safety and Health Administration.

Why are so many brands shifting ad spend to CTV?

For marketers who want a presence in streaming, Roku is the obvious place to go. With 47% of all streaming time in the US, it has more reach than every competitor. Discover how Roku Ads Manager can spread your message across 100+ premium apps in a single, self-serve ad buy.

Set up your campaign today.

Why the mill is running uranium again

The mill processed no conventional ore and produced no finished uranium concentrate in the third quarter, after making 867,442 pounds from April through June, a company executive told Skillings Mining Review on Nov. 17. He described the upcoming run as a three-to-five-month campaign.

Output from the run is meant to cover deliveries under the company's existing uranium supply contracts through 2028, with room for spot sales. Energy Fuels expects to sell 1.11 million pounds to utilities under long-term contracts in 2027, up 35% from 820,000 pounds in 2026. Once the run wraps up, the company plans to move the mill back to rare earth processing, starting with monazite already in inventory.

"At the same time, we recognize that production at our Pinyon Plain mine in Arizona is expected to wind down in the coming years," President and CEO Ross Bhappu said in the release. "We are therefore advancing several additional U.S. uranium projects that we believe will replace that production and provide opportunities for future growth."

Work at Utah mine sites

  • Energy Queen (La Sal area). Hoist rehabilitation is underway at the partially developed mine about 60 road miles north of the mill, including a new motor and skip cages plus upgrades to surface and underground electrical systems. The company says that work is needed to return the mine to active status.

  • Bullfrog (Henry Mountains district). At the undeveloped deposit about 100 road miles west of the mill, Energy Fuels is drilling four monitoring wells to set baseline groundwater conditions for permitting with the Utah Division of Oil, Gas and Mining and the U.S. Bureau of Land Management. One well is done, and the rest are expected by the end of 2026.

  • Whirlwind (Colorado-Utah border). Crews have dewatered the mine, rehabilitated the existing decline and started underground development. First production is scheduled for 2028, subject to permitting.

Together with the Nichols Ranch in-situ project in Wyoming, those projects could add about 1.25 million pounds of annual uranium production, the company said.

Energy Fuels is also building at the mill itself. On its third-quarter earnings call, Bhappu confirmed approval to begin construction of the Phase 1B and 1C heavy rare earth processing expansion at White Mesa, with completion expected in early 2028, Zacks Equity Research reported.

White Mesa is a big piece of Utah's critical minerals story. Gov. Spencer Cox has pointed to Utah being home to the nation's only conventional uranium mill, as UCMN reported from his critical minerals push. Nuclear power plans are also moving forward elsewhere in the state, including the Valar nuclear campus permit in Carbon County.

SPONSORED BY

Utah Safety Consultant – safety audits, written programs and OSHA training

This update is sponsored by Utah Safety Consultant: safety audits, written programs and OSHA training for Utah job sites. Call (435) 281-6999 or visit utahsafetyconsultant.com.

Get the free Friday magazine

Utah construction and mining projects, jobs and equipment news, once a week.

Keep Reading

View more
caret-right

Utah Construction and Mining News

Weekly Utah construction and mining magazine covering projects, equipment, jobs, mining, and industry news — with a listen-while-you-work show.

Archive

About →

Advertise →

Contact →

Privacy →

Terms →

Facebook →

LinkedIn →

Sister sites

BearLakeTV.com

Bear Lake Conservation

5 Stars Utah

© 2026 Utah Construction and Mining News.
beehiivPowered by beehiiv